Cipher Digital

CIFR-πŸ‡ΊπŸ‡Έ USA
Price
$6.40
as of Nov 6, 2026
Market cap
$2.9B
as of Nov 6, 2026

Sites & Capacity

Total active power (IT load)18 MW
In build capacity (IT load)408 MW
Owned capacity share100%capacity-weighted, vs colocation

Projected AI capacity (IT load)*

68 MWEoY 2026426426 MWEoY 20274266581,084 MWEoY 20284261,9152,341 MWEoY 2030
ContractedUncontracted

Active & in build (3)

Image
Site
CapacityIT load Β· theoretical gross
Est. capacityend of year, IT loadCommentaries
Wink, TX Β· USAUpdated Nov 2, 2026
Active
18 MW
In build
131 MW
Theoretical
β€”
2028
149 MW
2030
149 MW
β€”
Colorado City, TX Β· USAUpdated Nov 2, 2026
Active
β€”
In build
207 MW
Theoretical
β€”
2028
407 MW
2030
564 MW
Potential BTM Β· 500 MW gross
Andrews County, TX Β· USAUpdated Nov 2, 2026
Active
β€”
In build
70 MW
Theoretical
β€”
2028
170 MW
2030
170 MW
ERCOT: Base Load Β· 100 MW grossERCOT: Studied Load Β· 200 MW grossPotential BTM Β· 200 MW gross

Pipeline portfolio (announced) (8)

Site
Planned capacityEst. capacityend of year, IT loadCommentaries
Texas Β· USAUpdated Nov 2, 2026
70 MWgrossQ3 2027
2028
54 MW
2030
54 MW
ERCOT: Fully Interconnection-Approved Β· 70 MW gross
Cotulla, OH Β· USAUpdated Nov 2, 2026
200 MWgrossQ4 2027
2028
154 MW
2030
154 MW
ERCOT: Fully Interconnection-Approved Β· 200 MW gross
ColchisJV (95% owned)
Texas Β· USAUpdated Nov 2, 2026
1,000 MWgross2028
2028
150 MW
2030
500 MW
ERCOT: Base Load Β· 1,000 MW gross
Texas Β· USAUpdated Aug 4, 2026
500 MWgross2028
2028
β€”
2030
150 MW
ERCOT: Studied Load Β· 500 MW gross
Texas Β· USAUpdated Aug 4, 2026
500 MWgross2028
2028
β€”
2030
150 MW
ERCOT: Studied Load Β· 500 MW gross
Texas Β· USAUpdated Aug 4, 2026
500 MWgross2028
2028
β€”
2030
150 MW
β€”
San Antonio area, TX Β· USAUpdated Aug 4, 2026 Β· manual entry
900 MWgross2030
2028
β€”
2030
300 MW
ERCOT: Studied Load Β· 900 MW grossPotential BTM Β· 900 MW gross
Texas Β· USAUpdated Nov 2, 2026
70 MWtheoreticalβ€”
2028
β€”
2030
β€”
β€”

ERCOT β€” ERCOT (Electric Reliability Council of Texas) operates the Texas grid. A large new load only gets energized once it has cleared ERCOT's interconnection process, so the label a block carries says how far along that approval is: Fully Interconnection-Approved: every ERCOT approval is granted β€” the load can be energized as planned. Base Load: approved as firm load in ERCOT's planning models; energization still depends on the remaining steps. Studied Load: still in ERCOT's study queue β€” no firm approval yet.

Bitcoin mining (1)

SiteActive powerEst. capacityend of year, AI, IT loadCommentaries
Odessa, TX Β· USAUpdated Nov 2, 2026
207 MW
2028
β€”
2030
β€”
AI/HPC lease in discussion

*Projected AI capacity, bitcoin-mining sites excluded: the fleet online today, plus each block's remaining capacity once its scheduled delivery falls before that year end (the delivery end date; failing that the delivery start date; failing that the energization target plus one year), plus each pipeline site's planned capacity (the sum of its block targets, or its theoretical capacity when no block states one) one year after its first energization target. A bitcoin-mining site contributes only the AI capacity a block explicitly estimates for EoY 2028 β€” a conversion someone has assessed β€” counted in full, since what runs there today is mining. Past its last scheduled date, in 2027 and 2028 a site is assumed to keep adding its current in-build amount each year, up to its theoretical capacity in IT load. Blocks without a signed customer count in full (no haircut set in the common metrics).

** Estimated: the source reported this figure on a gross basis. It is shown in IT load by dividing by the PUE common metric, currently 1.3.