← Cipher Digital · Sites

Stingray

Under construction

Andrews County, TX · USA

ColocationOwnedEncumbered — pledged as collateral
Stingray — Nov 2, 2026Nov 2, 2026
Active (IT load)—
In build (IT load, excl. active)70 MW
Theoretical (gross)—

Deals · Amazon Web Services - 06/2026 (70 MW IT)

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1Amazon Web Services - 06/2026— / 70 MW IT— / 100 MW gross
Contracted
Construction start · Q2 2026Delivery end · Jun 30, 2027
—ERCOT: Base Load——
Phase 2—— / 200 MW gross
Speculative
Energization · 2030
—ERCOT: Studied LoadPotential BTM100 MW—
Total— / 223.8*** MW IT— / 300 MW gross

ERCOT — ERCOT (Electric Reliability Council of Texas) operates the Texas grid. A large new load only gets energized once it has cleared ERCOT's interconnection process, so the label a block carries says how far along that approval is: Base Load: approved as firm load in ERCOT's planning models; energization still depends on the remaining steps. Studied Load: still in ERCOT's study queue — no firm approval yet.

Financings (1)

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.