Black Pearl

ActiveUnder construction

Wink, TX · USA

ColocationOwnedEncumbered — pledged as collateral
Black Pearl — Nov 2, 2026Nov 2, 2026
Active (IT load)—
In build (IT load, excl. active)131 MW
Theoretical (gross)—

Deals · Amazon Web Services - 11/2025 (216 MW IT)

Blocks (6)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Data Hall 1Amazon Web Services - 11/2025— / 35 MW IT
Contracted
Construction start · Q1 2026Delivery end · Sep 30, 2026
————
Network Hall 1Amazon Web Services - 11/2025— / 15 MW IT
Contracted
Construction start · Q1 2026Delivery end · Sep 30, 2026
————
Data Hall 2Amazon Web Services - 11/2025— / 35 MW IT
Contracted
Construction start · Q1 2026Delivery end · Oct 30, 2026
————
Data Hall 3Amazon Web Services - 11/2025— / 35 MW IT
Contracted
Construction start · Q1 2026Delivery end · Dec 31, 2026
————
Network Hall 2Amazon Web Services - 11/2025— / 15 MW IT
Contracted
Construction start · Q2 2026Delivery end · Dec 31, 2026
————
Data Hall 4Amazon Web Services - 11/2025— / 81 MW IT
Contracted
Construction start · Q2 2026Delivery end · Feb 28, 2027
————
Total— / 216 MW IT— / 280.8*** MW gross

Financings (2)

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.