Q3 2026 earningsMon, Nov 2, 2026· Before market open

Cipher Digital reports third quarter 2026 results

Total Revenue26.7M USD
Adjusted EBITDA-9.96M USD
Net Income (Loss)31.61M USD
Total Contracted Power Portfolio0.7GW

Analysis

Good news: Cipher recognized its first HPC lease revenue and expanded the Barber Lake lease to a 20-year term, lifting contracted revenue there by $5.2 billion to $9.1 billion, while also gaining a conditional ERCOT base load classification for Colchis and growing its development pipeline to roughly 5.9 GW. The $31.6 million GAAP net income was driven mainly by a non-cash $127.2 million warrant fair-value gain, and Adjusted EBITDA remained negative (-$10.0 million), so underlying operating profitability has not yet caught up with the HPC buildout.

Key points

  • Q3 2026 revenue of $26.7 million and Adjusted EBITDA of negative $10.0 million, as the company recognized its first HPC lease revenue following rent commencement at Black Pearl.
  • Net income available to common stockholders was $31.6 million ($0.08 basic, $(0.22) diluted per share), driven largely by a $127.2 million gain on the fair value of warrant liabilities.
  • Expanded the Barber Lake lease to a 20-year term with a leading AI lab, lifting total contracted revenue at the site to approximately $9.1 billion (previously announced in September).
  • Delivered first capacity at Black Pearl, with 18 MW of critical IT capacity handed to the tenant to date; Stingray shell construction remains on track for completion in Q4 2026.
  • Received ERCOT Batch Zero conditional classifications, including a base load designation for 1 GW at Colchis, with final classifications expected in December 2026.
  • Began development of lateral natural gas pipelines to support up to 2.5 GW of on-site generation, and acquired Horizon, a 70 MW Texas site expected to energize in 2029.
  • Development pipeline now totals approximately 5.9 GW across 11 sites.
  • Completed the previously announced $850 million convertible notes offering (0.000% due 2032) to fund the Barber Lake lease expansion, with capped calls raising the effective conversion price to $28.35/share; equitized $165.9 million of 2030 convertible notes.

Site updates (8)

SiteStatusActiveIn buildTheoretical
ColchisTexas

Received conditional base load classification from ERCOT's Batch Zero process (1 GW); final classification expected December 2026. In discussions for an HPC hosting lease; target energization 2028.

Disclosed——1,000 MWgross
UlyssesCotulla, OH

Interconnection approved for 200 gross MW; substation development initiated. In discussions for an HPC hosting lease; target energization Q4 2027.

Disclosed——200 MWgross
ReveilleTexas

ERCOT interconnection approved for 70 gross MW; substation development initiated. In discussions for an HPC hosting lease; target energization Q3 2027.

Disclosed——70 MWgross
OdessaOdessa, TX

~296 BTC mined in Q3 2026 on a fixed-price PPA; ~11.6 EH/s total hashrate, ~17.2 J/TH fleet efficiency, ~$0.028/kWh power cost. Active discussions on HPC monetization continue.

Active——207 MWgross
StingrayAndrews County, TX

Steel erection progressing on schedule; shell construction expected complete in Q4 2026. Included in ERCOT's May 2026 Quarterly Stability Assessment, qualifying as base load with capacity not subject to further study or reallocation.

Under construction———
Black PearlWink, TX

First data center capacity delivered in August, ahead of schedule; 18 MW of critical IT capacity delivered to the tenant to date. Remaining Phase I data halls in MEP fit-out; Phase II foundations and building steel complete, electrical work in progress. ~256 additional acres acquired for expansion.

ActiveUnder construction18 MWIT——
Barber LakeColorado City, TX

First HPC capacity expected at Barber Lake in Q4 2026; construction on track to meet amended delivery milestones; tenant deploying compute throughout the facility; ~685 additional acres acquired for expansion.

Under construction———
HorizonTexas

Acquired in Q3 2026; 70 MW site in Texas expected to energize in 2029.

Disclosed——70 MWgross