NeoCapCompaniesValuationsScenariosMetrics

Core Scientific

CORZ-πŸ‡ΊπŸ‡Έ USA
Price
$11.70
as of Nov 6, 2026
Market cap
$3.8B
as of Nov 6, 2026

Sites & Capacity

Total active power (IT load)490 MW
In build capacity (IT load)629 MW
Owned capacity share100%capacity-weighted, vs colocation

Projected AI capacity (IT load)*

490490 MWEoY 20261,0091,009 MWEoY 20271,1191,119 MWEoY 20281,1195921,711 MWEoY 2030
ContractedUncontracted

Active & in build (8)

Image
Site
CapacityIT load Β· theoretical gross
Est. capacityend of year, IT loadCommentaries
Denton, TX Β· USAUpdated Nov 5, 2026
Active
260 MW
In build
β€”
Theoretical
260 MWIT
2028
260 MW
2030
260 MW
β€”
Dalton β€” no photo yet
Dalton, GA Β· USAUpdated Nov 5, 2026
Active
75 MW
In build
220 MW
Theoretical
175 MWIT
2028
295 MW
2030
295 MW
β€”
Muskogee β€” no photo yet
Muskogee, OK Β· USAUpdated Nov 5, 2026
Active
70 MW
In build
82 MW
Theoretical
70 MWIT
2028
152 MW
2030
544 MW
Potential BTM Β· 725 MW IT
Marble β€” no photo yet
Marble, NC Β· USAUpdated Nov 5, 2026
Active
65 MW
In build
β€”
Theoretical
65 MWIT
2028
65 MW
2030
65 MW
β€”
Austin β€” no photo yet
Austin, TX Β· USAUpdated Nov 5, 2026
Active
20 MW
In build
β€”
Theoretical
20 MWIT
2028
20 MW
2030
20 MW
β€”
Pecos β€” no photo yet
Pecos, TX Β· USAUpdated Nov 5, 2026
Active
0 MW
In build
185 MW
Theoretical
185 MWIT
2028
185 MW
2030
385 MW
Potential BTM Β· 815 MW IT
Hunt β€” no photo yet
Hunt County, TX Β· USAUpdated Nov 5, 2026
Active
0 MW
In build
110 MW
Theoretical
110 MWIT
2028
110 MW
2030
110 MW
ERCOT: Base Load Β· 302 MW IT
Auburn β€” no photo yet
Auburn, AL Β· USAUpdated Nov 5, 2026
Active
0 MW
In build
32 MW
Theoretical
32 MWIT
2028
32 MW
2030
32 MW
β€”

Bitcoin mining (1)

SiteActive powerEst. capacityend of year, AI, IT loadCommentaries
Pecos, TX Β· USAUpdated Nov 5, 2026
300 MW
2028
β€”
2030
β€”
Potential BTM Β· 815 MW IT

*Projected AI capacity, bitcoin-mining sites excluded: the fleet online today, plus each block's remaining capacity once its scheduled delivery falls before that year end (the delivery end date; failing that the delivery start date; failing that the energization target plus one year), plus each pipeline site's planned capacity (the sum of its block targets, or its theoretical capacity when no block states one) one year after its first energization target. A bitcoin-mining site contributes only the AI capacity a block explicitly estimates for EoY 2028 β€” a conversion someone has assessed β€” counted in full, since what runs there today is mining. Past its last scheduled date, in 2027 and 2028 a site is assumed to keep adding its current in-build amount each year, up to its theoretical capacity in IT load. Blocks without a signed customer count in full (no haircut set in the common metrics).

** Estimated: the source reported this figure on a gross basis. It is shown in IT load by dividing by the PUE common metric, currently 1.3.