← Core Scientific · Sites

Hunt

Under construction

Hunt County, TX · USA

ColocationOwned
Hunt — no photo yet
Active (IT load)—
In build (IT load, excl. active)110 MW
Theoretical (gross)110 MWIT

Deals · AMD - 07/2026 (377 MW IT)

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1AMD - 07/2026— / 110 MW IT
Contracted
Delivery start · Jan 1, 2028
—ERCOT: Base Load——
Phase 2—— / 192 MW IT
Speculative
——ERCOT: Base Load——
Total— / 302 MW IT— / 392.6*** MW gross

ERCOT — ERCOT (Electric Reliability Council of Texas) operates the Texas grid. A large new load only gets energized once it has cleared ERCOT's interconnection process, so the label a block carries says how far along that approval is: Base Load: approved as firm load in ERCOT's planning models; energization still depends on the remaining steps.

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.