← Core Scientific · Sites

Dalton

ActiveUnder construction

Dalton, GA · USA

ColocationOwned
Dalton — no photo yet
Active (IT load)75 MW
In build (IT load, excl. active)220 MW
Theoretical (gross)175 MWIT

Deals · Undisclosed customer - 07/2026 (152 MW IT) · CoreWeave - 02/2025 (390 MW IT)

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1CoreWeave - 02/202575 / 175 MW IT (43%)
ContractedEnergized
Delivery end · Mar 31, 2027
————
Phase 2Undisclosed customer - 07/2026— / 120 MW IT
Contracted
Delivery start · Jul 1, 2027
————
Total75 / 295 MW IT (25%)97.5 / 383.5*** MW gross (25%)

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.