Applied Digital Corporation
APLD-🇺🇸 USA
- Price
- $15.50
- as of Nov 6, 2026
- Market cap
- $4.7B
- as of Nov 6, 2026
NAV per share
$24.19+56% vs price
sum of the parts, on 349M diluted sharesFair value, rolled with the projections on record
1 Jan 2027$23.60+52% vs price · -2% vs NAV today
1 Jan 2028$30.52+97% vs price · +26% vs NAV today
Market
- Price
- $15.40latest close
- Market cap
- $4.69Bbasic shares
- Implied cap rate
- 8.12%12.3× NOI · model 7.17%
- EV per contracted MW
- $6.3M1410 MW signed · NOI/EV 19.5%
Scenario
Cap rate, bitcoin, and what each site has online by end-2030. Session only — the Valuations page stays on the base case.
Bear caseBase caseBull case
Base cap ratesigned leases and pipeline; tier spreads and the terminal spread held
Bitcoin pricethe 106 MW mining block is indexed to it
Projected AI capacity online at end-2030IT load — based on sites
PessimisticPrudentOptimistic
Polaris Forge 2
Finland
Unsited 2030 pipelineno site named yet
Sum-of-the-parts NAV
| Component | Per share | Running total | Basis |
|---|---|---|---|
| Signed leases, firm term | $43.63 | $43.63 | 6 leases, $1.74B/yr of stabilised NOI, discounted from rent commencement at the 7.17% base cap rate. |
| + Renewal options | +$0.00 | $43.63 | Each option period weighted by its probability of exercise, by holder: tenant, landlord or mutual. Rent held at the last firm-year level. |
| + Residual after options | +$18.32 | $61.94 | Re-let with nothing signed at the 8.42% terminal cap rate, after 10% re-leasing cost, discounted from the end of the options. |
| + Tenant quality premium | +$1.27 | $63.21 | Hyperscalers capitalised 100 bp below the base rate and frontier labs 50 bp below; investment-grade non-hyperscalers 25 bp above, neoclouds 200 bp above, third-party backstops halfway. |
| + Uncontracted pipeline to end-2028 | +$1.98 | $65.19 | 182 MW expected online by end-2028 with no tenant, valued as the lease it would become: $2.20M/MW of annual contract value at a 2027-07 signing, 85% margin over 15 firm years plus the residual, less $12M/MW of capex and the execution haircut — $7.6M per MW net — at 50% probability, a signature weight rising as delivery nears. |
| + Uncontracted pipeline, 2029-2030 | +$3.92 | $69.11 | 903 MW more with no tenant by end-2030 (block-level 2030 estimates and 275 MW guided with no site named), valued as the lease it would become at a 2029-07 signing — $2.20M/MW of annual contract value, $6.0M per MW net of capex and the execution haircut — at 25% probability, further from delivery than the 2028 tranche. |
| + Bitcoin mining | +$1.20 | $70.31 | 106 MW of fleet, net of the HPC capacity contracted on the same sites, at $3M/MW, indexed ×1.31 to BTC at $86,198 on 2026-09-22. |
| − Capex still owed | −$26.34 | $43.97 | 1,078 MW contracted and not yet delivered, allocated to the latest-starting leases × $12M/MW, × 100% owned, on the build schedule. Cash on hand of $3.68B covers 40% of it; financing already raised is not netted here because its proceeds sit in cash and net debt — what is still to raise is priced on the financing line. |
| − Execution haircut on undelivered MW | −$4.33 | $39.64 | 20% probability that the 1,078 MW contracted and not yet delivered never come online. Their NOI legs and the capex they would require are both taken at 80%, so this line is the expected value lost, net of the capex saved. The uncontracted pipeline keeps its own probability and is not haircut twice. |
| − Financing gap on unfunded capex | −$3.23 | $36.41 | $11.00B of build still to pay, plus $3.80B for the uncontracted pipeline at the probability counted above, against $3.68B of cash, $430M of committed undrawn facilities and $1.59B closed since the balance-sheet date: $9.10B has to be raised. Taken at 15% — the cost of raising it as equity below NAV or as project debt above the cap rate — on the build schedule. |
| − Net debt | −$7.74 | $28.66 | Gross debt less cash, at the latest balance sheet. |
| − Preferred and minority claims | −$5.77 | $22.89 | Redeemable preferred or minority interests ranking ahead of the common, at the latest balance sheet. Balance-sheet debt does not include them. |
| + In-the-money converts as equity | +$1.29 | $24.19 | Convertibles priced to convert leave net debt; their 46.2M conversion shares join the divisor. Every per-share figure here divides by 349M diluted shares. |
| NAV per share | $24.19 | price $15.40 | on 349M diluted shares |
Every row is a named, priced assumption; the implied cap rate says at what rate the market capitalises this book.
Data and assumptions
| Balance sheet and share count | ||
| Basic shares outstanding | 302.4M | Basic Shares Outstanding · Oct 6, 2026 |
| Cash and restricted cash | $3.68B | Total Cash and Restricted Cash · Aug 31, 2026 |
| Net debt | $2.70B | Total Debt · Aug 31, 2026 |
| Committed undrawn facilities | $430M | Financing |
| Capital closed since the balance-sheet date | $1.59B | |
| Preferred and minority claims | $2.01B | Total Debt · Aug 31, 2026 |
| In-the-money convertibles | $450M · 46.2M shares | Financing |
| Capacity | ||
| Signed leases | 6 · 1,410 MW contracted | Deals |
| AI capacity online today | 332 MW | Sites & Capacity |
| AI capacity at end-2028 | 1,592 MW · 89% contracted | |
| AI capacity at end-2030 | 2,220 MW · 64% contracted | |
| Unsited 2030 pipeline, half counted | 275 MW | |
| Mining fleet, net of leases on the same sites | 106 MW | |
| Owned capacity share | 100% | |
| Lease assumptions | ||
| Base cap rate | 7.17% · 13.9× NOI | 10-year Treasury 4.84% (2026-11-05) + 2.33 pts |
| Hyperscaler / frontier lab spread | −100 bp / −50 bp | Convention · source |
| IG corporate / neocloud spread | +25 bp / +200 bp (backstop: half) | |
| NOI margin (modified gross / triple net) | 85% / 97% | Trend in the sector's recent communications · source |
| Renewal probability (tenant / landlord option) | 50% / 90% | Convention · source |
| Terminal cap rate · re-leasing cost | 8.42% · 10% | 10-year Treasury 4.84% (2026-11-05) + 2.33 pts + 1.25 pts terminal premium |
| Capex per MW | $12M | Convention |
| Execution haircut on undelivered MW | 20% | Convention · source |
| Financing haircut on unfunded capex | 15% | Convention · source |
| Pipeline (uncontracted capacity) | ||
| Signature probability (within a year / 2-3 years / beyond) | 90% / 50% / 25% | Convention · source |
| Firm term of a future lease · signing lead | 15 years · 1.5 years before delivery | Convention · source |
| Annual contract value per MW at signing (evolving) | 2026: $2.00M / $2.20M · 2027: $2.20M · 2028: $2.20M · 2029: $2.20M · 2030: $2.20M | evolving metric |
| Bitcoin | ||
| EV per mining MW | $3M | Convention · source |
| BTC reference · latest close | $65,617 · $86,198 | BTC close on the day the EV per MW was read |
How the NAV is built
- Signed leases — the contract's average rent, or its escalating profile when the published total contains the escalator; converted to NOI at the margin of the lease structure, or at the issuer's own NOI figure when plausible; discounted year by year from the date rent starts. Without a published date the announcement date is used, and the row says so.
- Options — each extension period weighted by its probability of exercise, which depends on who holds it. A tenant option is exercised only if the market has risen; it is worth less to the landlord than a mutual option or its own.
- Residual — once the options run out, re-letting with nothing signed: the last NOI net of re-leasing cost, capitalised at the terminal cap rate, deliberately above the contracted one.
- Tier premium — hyperscalers below the base rate, frontier labs less far below (unrated, but signing 15-20 year take-or-pay leases their own model depends on), investment-grade non-hyperscalers slightly above (a good credit that does not need the compute for itself), neoclouds further above, third-party backstops halfway. Shown on its own line so the bonus is legible.
- Pipeline — capacity expected online with no tenant, valued as the lease it would become: the annual contract value per MW read at the signing date (the evolving series, delivery less the signing lead), the base NOI margin over a typical firm term plus the residual, less the capex the landlord bears and the execution haircut of a signed lease — then a conversion probability that rises as delivery nears. Two tranches: what the sites schedule by end-2028, then what the block-level 2030 estimates and the unsited 2030 pipeline add over 2029-2030. Signed leases never use the series — they carry their own contract terms. Nothing beyond 2030 is counted.
- Mining — the fleet at the group's EV per MW, JV-weighted, indexed to the latest BTC close over the calibration price. Net, site by site, of the HPC capacity already contracted there: a lease signed on a mining campus converts that power, so it cannot also be counted as a fleet (Pecos, Rockdale, Lake Mariner).
- Ownership and claims — each lease is taken at the share of its economics the listed company owns (Applied Digital's HPC leases at 85%, Macquarie holding the rest); redeemable preferred and minority interests are deducted alongside net debt; convertibles priced to convert are treated as equity, their principal leaving net debt and their conversion shares joining the divisor; warrants struck below the price are taken as exercised, their strike proceeds coming in and their shares joining the divisor (Core Scientific's 96M emergence warrants at $6.81).
- Firm-term NAV — the same sum with only the signed leases over their firm term: no options, no residual, no pipeline. The floor the market evidently prices to.
- Deductions — capex on contracted MW not yet delivered, allocated to the latest-starting leases at the capex per MW each landlord bears (zero where the tenant funds the build), on the build schedule; and net debt. A build whose financing is complete still owes its capex: the money raised is already counted in cash and net debt, so removing the capex would count it twice.
- Execution haircut — a signed lease on a site still under construction can slip or never be delivered. The undelivered share of each lease is taken at a probability of delivery: its NOI legs and its capex are scaled together, so the line is the expected value lost, net of the capex saved. The uncontracted pipeline carries its own probability and is not haircut twice.
- Financing gap — the build still to pay, less cash, committed undrawn facilities and capital closed since the balance-sheet date, is what has to be raised; a share of it is deducted as the cost of raising it, equity below NAV or project debt above the cap rate. Financing already raised is not netted from the capex: its proceeds sit in cash and net debt.