IREN's 2GW Sweetwater Hub included as base load in ERCOT Batch Zero

Key points

  • 2GW Sweetwater Hub (Sweetwater 1 and Sweetwater 2) conditionally included in ERCOT's Batch Zero process as Base Load
  • Sweetwater 1 (1,400MW) and Sweetwater 2 (600MW) form part of IREN's announced >5GW global development portfolio
  • At Sweetwater 1, the high-voltage substation was energized earlier this year; construction of 300MW (gross) of data center capacity continues, delivery targeted Q4 2027
  • Additional pipeline projects also included in Batch Zero, to be added to the announced portfolio once grid connection agreements are executed
  • ERCOT classifications remain conditional and subject to ongoing approval processes

Site updates (2)

SiteStatusActiveIn buildTheoretical
Sweetwater 1Sweetwater, TX

ERCOT Batch Zero conditional Base Load inclusion. High-voltage substation energized earlier in 2026; 300MW (gross) of data center capacity under construction, delivery targeted Q4 2027. Active MW not restated.

Under construction—300 MWgross1,400 MWgross
Sweetwater 2Sweetwater, TX

ERCOT Batch Zero conditional Base Load inclusion as part of the 2GW Sweetwater Hub. No construction or active figures stated for Sweetwater 2.

Disclosed——600 MWgross