← IREN · Sites

Sweetwater 1

Under construction

Sweetwater, TX · USA

Full-stack GPU cloudOwnedliquid
Sweetwater 1 — no photo yet
Active (IT load)—
In build (IT load, excl. active)300 MWgross
Theoretical (gross)1,400 MW

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1—— / 300 MW gross
SpeculativeEnergized
Energized · May 1, 2026Delivery start · Dec 31, 2027
Liquid (site default)———
Phase 2—— / 1,100 MW gross
Speculative
—LiquidERCOT: Base Load300 MW785 MW
Total— / 1,000*** MW IT— / 1,400 MW gross

ERCOT — ERCOT (Electric Reliability Council of Texas) operates the Texas grid. A large new load only gets energized once it has cleared ERCOT's interconnection process, so the label a block carries says how far along that approval is: Base Load: approved as firm load in ERCOT's planning models; energization still depends on the remaining steps.

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.4), because the blocks do not all state this one.