← Terawulf · Sites

Justified

Under construction

Hawesville, KY · USA

ColocationOwned
Justified — no photo yet
Active (IT load)—
In build (IT load, excl. active)401 MW
Theoretical (gross)482 MW

Deals · Anthropic - 07/2026 (401 MW IT)

Blocks (1)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1Anthropic - 07/2026— / 401 MW IT
Contracted
Delivery start · Dec 31, 2027Delivery end · Jun 30, 2028
————
Total— / 401 MW IT— / 521.3*** MW gross

Financings (3)

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.