← Hut 8 · Sites

Beacon Point

Under construction

Nueces County, TX · USA

ColocationOwnedEncumbered — pledged as collateral
Beacon Point — Nov 4, 2026Nov 4, 2026
Active (IT load)—
In build (IT load, excl. active)704 MW
Theoretical (gross)—

Deals · Undisclosed customer - 07/2026 (352 MW IT) · Undisclosed customer - 05/2026 (352 MW IT)

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1Undisclosed customer - 05/2026— / 352 MW IT
Contracted
Delivery start · Sep 30, 2027
—ERCOT: Base Load——
Phase 2Undisclosed customer - 07/2026— / 352 MW IT
Contracted
Delivery start · Jun 30, 2028
—ERCOT: Base Load——
Total— / 704 MW IT— / 915.2*** MW gross

ERCOT — ERCOT (Electric Reliability Council of Texas) operates the Texas grid. A large new load only gets energized once it has cleared ERCOT's interconnection process, so the label a block carries says how far along that approval is: Base Load: approved as firm load in ERCOT's planning models; energization still depends on the remaining steps.

Financings (1)

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.