Tue, Sep 22, 2026

Fermi and TensorWave extend lease closing date to October 31, 2026

Key points

  • First amendment to the 222 MW (gross) Project Matador data center lease moves the closing date from September 30 to October 31, 2026; all other terms are unchanged
  • The lease is worth about $6.5 billion over its initial 15-year term and is not effective until its closing conditions are met
  • Remaining conditions: work letters and guaranties, operations schedules and a service-level agreement, board approvals, and project-level financing sufficient to fund construction
  • Fermi is still negotiating a guaranty of the lease obligations with an investment-grade counterparty; the extension gives time to finalize it

Deal amendment

Amendment · Tue, Sep 22, 2026View the deal
DealProject Matador · TensorWave