Childress
ActiveUnder constructionChildress, TX · USA
Nov 5, 2026Deals · NVIDIA - 05/2026 (60 MW IT) · Microsoft - 11/2025 (200 MW IT) · poolside - 04/2024 · poolside - 02/2024
Blocks (4)*
| Block | Deal | Current / targetdelivered share | Status | Schedule** | Cooling | Misc | Est. Capacity - EoY 2028IT load | Est. Capacity - EoY 2030IT load | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Horizon 1-4 | Microsoft - 11/2025 | 50 / 200 MW IT (25%)— / 300 MW gross | ContractedEnergized | Delivery start · Sep 30, 2026Delivery end · Jan 31, 2027 | Liquid | — | — | — | |||
| Childress Air-Cooled 2026 | — | — / 50 MW gross | ContractedEnergized | Delivery end · Dec 31, 2026 | Air | — | — | — | |||
| Horizon 5-6 | — | — / 150 MW gross | SpeculativeEnergized | Delivery start · Dec 31, 2027 | Liquid | — | — | — | |||
| Childress Air-Cooled 2027 | — | — / 250 MW gross | SpeculativeEnergized | Delivery start · Dec 31, 2027 | Air | — | — | — | |||
| Total | 50 / 521.4*** MW IT (10%)70 / 750*** MW gross (9%) | ||||||||||
Financings (1)
*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.
**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.
*** Converted from the other basis with the PUE common metric (currently 1.4), because the blocks do not all state this one.