Mackenzie

ActiveUnder construction

Mackenzie, BC · Canada

Full-stack GPU cloudOwned
Mackenzie — no photo yet
Active (IT load)—
In build (IT load, excl. active)72 MW
Theoretical (gross)—

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1—— / 72 MW IT— / 80 MW gross
ContractedEnergized
Delivery end · Dec 31, 2026
————
Liquid-cooled expansion—— / 100 MW gross
Speculative
Construction start · Q1 FY27
————
Total— / 143.4*** MW IT— / 180 MW gross

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.4), because the blocks do not all state this one.