Applied Digital brings additional 75 MW online at Polaris Forge 1

Key points

  • Ready for Service achieved for the second phase of Building 2 at Polaris Forge 1 (Ellendale, North Dakota), adding 75 MW of critical IT load across three 25 MW data halls.
  • Building 2 is now complete at its full 150 MW of critical IT load.
  • Fully operational critical IT load at the campus reaches 250 MW, following the 100 MW first building and the initial 75 MW phase of Building 2.
  • The fully leased campus is contracted to deliver 400 MW of critical IT load at full buildout.

Site update

SiteStatusActiveIn buildTheoretical
Polaris Forge 1Ellendale, ND

Building 2 second phase Ready for Service 2026-10-02: +75 MW critical IT load across three 25 MW data halls; Building 2 complete at 150 MW; campus operational critical IT load 250 MW (100 MW Building 1 + 150 MW Building 2); fully leased campus contracted for 400 MW critical IT load at full buildout. Remaining capacity (Building 3) not quantified in this release.

ActiveUnder construction250 MWIT—400 MWIT