← CleanSpark · Sites

Brazoria

Brazoria County, TX · USA

ColocationOwned
Active (IT load)—
In build (IT load, excl. active)—
Theoretical (gross)600 MW

Blocks (2)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Phase 1—— / 300 MW gross
Speculative
Energization · Q4 2027
—ERCOT: Base Load——
Phase 2—— / 300 MW gross
Speculative
Energization · mid-2028
—ERCOT: Studied Load0 MW214 MW
Total— / 461.5*** MW IT— / 600 MW gross

ERCOT — ERCOT (Electric Reliability Council of Texas) operates the Texas grid. A large new load only gets energized once it has cleared ERCOT's interconnection process, so the label a block carries says how far along that approval is: Base Load: approved as firm load in ERCOT's planning models; energization still depends on the remaining steps. Studied Load: still in ERCOT's study queue — no firm approval yet.

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.