Wed, Oct 29, 2025
CleanSpark enters Texas with Greater Houston land and power acquisition
Key points
- Acquired rights to approximately 271 acres of land in Austin County, Texas, in the Greater Houston area
- Executed long-term power supply agreements totaling 285 MW to support a next-generation AI data center campus
- Transactions increase power under contract by 28%; consideration was cash plus common stock at closing, with additional cash payable on post-closing events
- Substation construction plan underway with long lead time items secured; site design and development to begin immediately
- Energization of more than 200 MW expected in the first half of 2027
Site update
| Site | Status | Active | In build | Theoretical |
|---|---|---|---|---|
SealyAustin County, TX ~271 acres, 285MW of long-term power supply agreements; energization of 200+MW expected H1 2027; part of Texas portfolio under LOI/exclusivity with Sandersville tenant | Under construction | 0 MW | — | 285 MWgross |