← Terawulf · Sites

Lake Mariner

ActiveUnder construction

Barker, NY · USA

ColocationOwnedEncumbered — pledged as collateral
Lake Mariner — no photo yet
Active (IT load)102 MW
In build (IT load, excl. active)498 MW
Bitcoin mining (active)245 MW
Theoretical (gross)438 MWIT

Deals · Fluidstack - 08/2025 (2) (160 MW IT) · Fluidstack - 08/2025 (200 MW IT) · Core42 - 12/2024 (72.5 MW IT)

Blocks (7)*

BlockDealCurrent / targetdelivered shareStatusSchedule**CoolingMiscEst. Capacity - EoY 2028IT loadEst. Capacity - EoY 2030IT load
Wulf DenCore42 - 12/20242 / 2 MW IT (100%)
Contracted
—————
CB-1Core42 - 12/202416 / 16 MW IT (100%)
Contracted
—Liquid———
CB-2Core42 - 12/202442 / 42 MW IT (100%)
Contracted
—Liquid———
CB-3Fluidstack - 08/202542 / 42 MW IT (100%)
Contracted
—Liquid———
CB-4Fluidstack - 08/2025— / 168 MW IT
Contracted
Energization · Q3 2026Delivery start · Dec 31, 2026
Liquid———
CB-5Fluidstack - 08/2025 (2)— / 168 MW IT
Contracted
Delivery start · Mar 31, 2027
Liquid———
Expansion—— / 162 MW IT— / 200 MW gross
Speculative
Delivery end · 2029
————
Total102 / 600 MW IT (17%)132.6 / 769.4*** MW gross (17%)

Financings (1)

*Blocks follow a site's build-out over time; an expansion is a new block. A deal can span several blocks — picking a deal in the form prefills its remaining contracted capacity, net of what its other blocks already target. Power figures are recorded on the basis the source reported, IT load and/or gross.

**A block's capacity is taken to come online at its delivery end date (the actual date when one is recorded, otherwise the target); failing that at its delivery start date; failing that one year after its energization target. That resolved date is what the capacity estimates on the Sites & Capacity tab use.

*** Converted from the other basis with the PUE common metric (currently 1.3), because the blocks do not all state this one.