TeraWulf expands Muskie contracted power to 1 GW

Key points

  • Subsidiary DB Long Hunts Data LLC amended its transmission and energy service agreements with Kentucky Power (an AEP company) on October 1, 2026
  • Contracted power capacity at the Muskie Data Campus in eastern Kentucky increased from 500 MW to 1 GW
  • Second 500 MW phase delivery moved up from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule
  • First 500 MW phase remains targeted to begin ramping in 2028
  • Company also intends to upsize its existing senior secured revolving credit facility and raise additional senior secured debt to support letter-of-credit needs tied to its power development partnerships with utilities

Site update

SiteStatusActiveIn buildTheoretical
MuskieGrayson, KY

Amended & Restated KY Power Agreements (executed Oct 1, 2026) firm up contracted power capacity at Muskie to 1 GW (500 MW + 500 MW); second 500 MW phase delivery moved from 2030 to 2029, subject to KY PSC approval and Kentucky Power's construction schedule; first 500 MW phase still targeted to begin ramping in 2028.

Disclosed——1,000 MWgross